Road construction up-date
The following information was sent to the County last Thursday so the “tomorrow” reference is for Friday 4/18.
Hello,
The box culvert and cattle pass removal have been completed and starting tomorrow we will move west to the section between CTH P and CTH O. Working west to east with culvert replacement – there is a culvert near CTH P that will start and should be completed tomorrow (weather dependent), then Monday/Tuesday will be a culvert by the WiDNR parking lot, followed by a very deep culvert just west of CTH O the rest of the week. The section between CTH P and CTH O will be open to local traffic in areas the crew isn’t working but traffic will not be able to continue straight through from CTH P to CTH O during the daytime.
Some of the additional detour signage has been installed. Hopefully, those are helping keep people on the detour.
Operations this Week:
- Completed the box culvert construction and cattle pass removal
- Begin culvert replacements between CTH P and CTH O (Friday and next week)
- Restoration/topsoil of areas around culverts
Operations for Next Week:
- Continue working on culverts between CTH P and CTH O
- Asphalt patching in completed culvert areas
- The week of 4/28, move operations between CTH H and WIS 67
US 12 (From Whitewater)
Traffic:
- Local Traffic Only: Area between CTH P and CTH O will have closures starting tomorrow (Friday 4/18). Area between CTH O to WIS 67 is locals only.
- If traveling to Elkhorn and beyond, use the posted detour – CTH P to CTH A, CTH A to CTH ES, CTH ES back to US 12.
US 12 (From Elkhorn)
Traffic:
- Local Traffic Only: Area between WIS 20/67 to just west of CTH O will be open to local traffic only.
- If traveling to Whitewater, use the posed detour – CTH ES to CTH A, CTH A to CTH P, CTH P back to US 12.
- WIS 67/WIS 20 will be open so follow US 12 north to WIS 67/WIS 20 and go north or east as needed.