Roads
US 12 opening for traffic
Information just received from the County… As of this moment, US12 will be reopened today. I don’t have an official time because they are working on taking the temporary signals down right now. Once that is done, the barricades will be removed. If there is an issue and it isn’t reopening, the County…
Read MoreLatest on Hwy 12 and Cty P
Received from Walworth County Public Works Hello, The pavement marking crews have been working hard all week and are mostly completed. The restoration and signing crews have also completed their work this week. The remaining work preventing US 12 from opening is the signal at US 12/County P. WE Energies was delayed in installing…
Read MoreChange to construction schedule Clover Valley Rd
The Clover Valley road repair will begin Monday, July 21st, and not Tuesday, July 22nd, as previously posted. This change was made by the construction company.
Read MoreTownship road construction to begin 7-22
FYI!! The following two road projects will begin week of 7/20/2025 Clover Valley Rd between Anderson Road and Millis Road: July 22 – July 24 Woodward Road: July 24 – will begin repaving No end date has been determined. All road work is subject to weather conditions. Thank you! Be safe!
Read MoreLengthy update on road construction
The asphalt paving crews started placing the final layer of asphalt today (the Wednesday rains delayed that start). The paving crews will be on site tomorrow and will continue 6 days a week until completed (barring any weather delays). With the forecasted temperatures tomorrow and Monday, they will get as far as they can…
Read Moreconstruction up-date from County
Work week – 6/16 through 6/20 Cross-culvert work east of Hwy 89. Work section is East of Johnson Rd to just West of Holiday Dr. One cross-culvert is being done each day this week. Every location requires a HARD CLOSURE, no vehicles will get through during the day. End of work day, hole will…
Read More